  • Client

    Nigeria Gas Company

    Project Scope

    The Major Scope of the Project consists of:

    • PCI of Bi-directional pig traps, condensate tank and actuated ball valves and fittings for the pipeline system.

    Challenges

    • Major road crossing by HDD;
    • New facility development within live gas and power facility;
    • Right of way (ROW) with two (2) parallel high pressure gas lines;
    • ROW category class one (1) population density.

    Location

    Obigbo, Rivers State–Nigeria.

    Completion Date

    2015

    Man Hours 85,580 Man Hours



NOPL OBIGBO 24” INTERCONNECTION GAS PIPELINE PROJECT

  • Thrust Bore Pipe Laying.

  • Job Completion.

  •